EQUIPMENT FOR HIRE

Access Earthmoving Lighting Site Accommodation Air & Air Accessories Floor & Cleaning Materials Handling Tools & Equipment Concrete & Masonry Generators & Power Distribution Pipeline Testing Traffic Management Confined Space Entry Ladders & Scaffolding Propping & Structural Support Trucks Vehicles & Trailers Compaction Landscaping Pumps & Fluid Management Welding Construction Lasers Lift & Shift Shoring View All Equipment

SOLUTIONS

Engineering Solutions Industrial Solutions Resources   Design & Installation Project Planning Past Projects   Water Management Equipment Solutions Latest News   Traffic Management Systems & Experience View all Solutions

TRAINING COURSES

Asbestos Removal Electrical Safety Laser Safety Underground Assets Confined Space Elevated Work Platforms Load restraint & plant safety VOC Construction and Small Equipment Forklift Traffic Control Work at Heights       View all Training Courses
fas fa-shopping-cart Hire Now fas fa-map-marker-alt Find a branch fas fa-phone 13 15 52
fas fa-bars Hire Solutions Training fas fa-shopping-cart Hire Now fas fa-map-marker-alt Find a branch fas fa-phone 13 15 52 fas fa-user Coates Connect About us Contact us

WOLLI CREEK PUMP STATION

LATEST FROM US

The pumping station site sat at 9 metres below ground level, in poor soils. When excavations started Sydney Water hit the water table at around 3 metres in depth, meaning increased risk of subsidence in the pit walls and inundation at the base of the excavation.

Sydney Water contracted Coates Hire Engineering and Technical Services, to design, build, test and install a shoring system that would hold the sheet pile walls of the pit, while also dewatering the excavation site so the works could be carried out.

Temporary Works Engineer at Coates Hire Engineering and Technical Services Team, Darren Browne, says the pumping station at Wolli Creek was a complicated site which needed to be secured before workers could safely operate.

“Because the Mega Brace system pushes back on the walls, with adjustable hydraulic rams, we have a certain amount of flexibility to reconfigure the shoring and adjust to the changing conditions, unlike traditional steel bracing”
Darren Browne Temporary Works Engineer Coates Hire

The groundwater was controlled with a large spear-point system, installed to achieve sufficient suction lift at the required flow rates.

Sydney Water Construction Co-ordinator Colin Burrell says due to the soil quality and high water table at the site, the excavation required a fit-for-purpose shoring and dewatering design to ensure that the work could be carried out safely and economically.

“We had groundwater sitting at 3 metres below the surface, which the wall had to retain. The dewatering system needed to keep the pit dry at all times,” he says.

He says the project was completed without customer complaint or disruption to wastewater services. “The Coates Hire team was very professional and they were able to adapt their designs and their approach according to the new conditions. They allowed us to push forward on the project knowing that the shoring and dewatering issues were being dealt with.”

SHARE THIS ARTICLE

{{ socialIcon(api.type) }} {{ socialIcon(api.type) }} {{ socialIcon(api.type) }}
Find out how we can help with your project fas fa-phone-alt CALL US 13 15 52 Submit Enquiry

By submitting this enquiry you agree to Coates Hire's Communications Terms & Conditions

Give us a call
fas fa-phone-alt 13 15 52 fas fa-check 24/7 Online Services fas fa-check Safety Standard Guarantee fas fa-check Same day delivery available
far fa-times-circle Your enquiry has been submitted

Thank you for your enquiry. One of our team members will get back to you as soon as possible.